< back to menu          Please scroll down to view selected projects

Location:    Bacton Interconnector  Pipeline, Norfolk, England

Client:        Bacton Balgzand Ltd

Engineering, Landfall and Construction

Landfall section at the UK end of the Bacton Balgzand (Netherlands) Interconnector pipeline.  The work included pre dredging a trench and pull ashore from a lay barge of a 1.0km x 36” dia steel, using an L&M 600 te linear winch pulling system and the construction of a tunnel and shaft to bring the pipeline from the beach into the Bacton terminal.

  

Location:    Ross Bay, Dumfries, Scotland

Client:        Bord Gais  Eireann

Engineering, Landfall and Construction

Landfall section of the Gas 2025 – 2nd Scotland to Ireland Interconnector at Ross Bay.  Work included pre dredging trench and pull ashore from lay barge of a 1.0km x 610mm dia steel.  Work also included 1.2km of landline to new compressor station.

  

Location:    St Fergus, Aberdeenshire, Scotland

Client:        Britannia Operator Ltd

Engineering, Landfall, Trenching and Construction

Installation of the landfall section of the Britannia Field gas pipeline. Work included the excavation of a primary dune and driving a 130m beach cofferdam prior to the pull ashore of a 1km x 711mm dia pipeline. The inshore section was subsequently post buried into the seabed using the trenching machine TMIV operating from the workbarge LM Balder.  A further 1.2km of land line was installed linking the landfall to the gas reception terminal.

  

Location:    Bacton, Norfolk, England

Client         Interconnector Group

Engineering, Landfall and Construction

Sinking of a 24m shaft and 115m tunnel through cliff, dredging of a 1.2km shore approach trench, construction of a beach cofferdam and the pull ashore of the 1.2km x 1016mm gas pipeline and a 1km x 508mm temporary test water discharge pipe from laybarge.  Part of the UK to Europe interconnector gas transfer pipeline.

  

Location:    Point of Ayr, North Wales, Wales

Client:        Hamilton Oil (s/c to McDermott/ ETPM)

Engineering, Landfall, Trenching and Construction

Fabrication on land and pulling into position by barge mounted winches on the LM Balder.  The 4.15km long x 508mm gasline + 2 No. 90mm dia condensate piggyback pipelines forming the landfall section of the Hamilton Field development in Liverpool Bay.  The pipelines were post buried to give a 2m minimum cover using a trenching machine TMIV.

  

Location:    Brighouse Bay, Dumfries, Scotland

Client:        Bord Gais Eireann

Engineering, Landfall and Construction

Landfall section of the Scotland - Eire Interconnector Gas Pipeline at Brighouse Bay. Work included pre dredging trench and pull ashore from lay barge of a 3.3km x 610mm dia steel pipeline.

  

Location:    Tees-side, England

Client:        Amoco UK Exploration Co.(s/c to ETPM)

Engineering, Landfall and Construction

The landfall section of the CATS (Central Area Transmission System) pipeline at Tees-side.  Work included a 4.5km, 1200 tonne pull ashore of a 915mm dia steel pipeline into a pre-dredged trench having an average depth of 3.5m and the construction of a 110m beach cofferdam and 400 metres of land pipeline.

  

Location:    Cruden Bay, Aberdeenshire, Scotland

Client:        BP Petroleum Development Ltd

Engineering, Landfall and Trenching

Landfall section of the Forties Field replacement pipeline.  Work included an open cut excavation through a primary sand-dune, the driving of a beach/dune cofferdam and the pull ashore of a 1.5km x 915mm dia steel pipeline from a laybarge.  The inshore 1.5km section was then jetted into the seabed using the trenching machine TM IV.  A further 16.5km of the pipeline was trenched to give 0.25m of cover using the 'post pipelay' plough PBP1.  Both trenching operations were supported by the workbarge LM Balder.

  

Location:    St Fergus, Aberdeenshire, Scotland

Client:        BP Petroleum Development Ltd (s/c to ETPM)

Engineering, Landfall and Trenching

Landfall section of the Miller Field pipeline.  Work included major open cut excavation through a primary sand-dune, the driving of a beach/dune cofferdam and the pull ashore of a 1.5km x 762mm dia steel pipeline from a laybarge.  The inshore 1.5km section was then jetted into the seabed using the trenching machine TM IV operating from LM Balder.

  

Location:    St Fergus, Aberdeenshire, Scotland

Client:        Mobil North Sea Ltd (s/c to EMC)

Engineering, Landfall, Construction and Trenching

Landfall section of the Beryl Field pipeline.  Work included excavation of primary dune and driving a 250m long beach cofferdam.  The pull ashore of a 762mm gas trunk line and a 323mm outfall pipe, each 800m long, in a 1200 tonne pulling operation, from a laybarge anchored offshore.  The pipelines were subsequently buried into the seabed using trenching machine TMIV operating from the workbarge LM Balder.  Ancillary works included 1.5km of landlines, valve station and pigging facility.

  

Location:    Theddlethorpe, Lincolnshire, England

Client:        Conoco UK Ltd

Engineering, Landfall and Construction

The landfall section of the SBGD LOGGS Gas pipeline.  Work included a 1200 t pull ashore of a 1.2km x 915mm dia steel pipeline with a 100mm dia piggyback methanol line into a pre-dredged trench and a 1.17km landline section with valve station, pig receiver and access road.

  

Location:    Bacton, Norfolk, England

Client:        Shell UK Exploration & Production Ltd (s/c to Saipem)

Engineering, Landfall and Construction

Sinking of a 12m shaft and 60m tunnel through cliff, dredging of a 700m shore approach trench, construction of a 100m long beach cofferdam and the 1.2km pull ashore of the 762mm dia SE Inde Field gas line from a laybarge.

  

Location:    Easington, Humberside, England

Client:        BGC          

Engineering, Landfall and Construction

The pull ashore of the 1km x 915mm dia Rough Field gas pipeline from a laybarge into a dredged trench

  

Location:    Sullom Voe, Shetland Islands, Scotland

Client:        Shell UK Exploration & Production Ltd (s/c to Oceanics)

Engineering, Landfall and Construction

Three contracts relating to Cormorant Field oil pipeline.  Preparation of seabed in depths up to 95m involving blasting, and deposition and levelling of graded stone, shore approach and pull ashore of the 914mm dia. wrapped and concrete-coated steel pipe and subsequent protection and securing of the line

  

Location:    St Fergus, Aberdeenshire, Scotland

Client:        Total Oil Marine (s/c to ETPM)         

Engineering, Landfall and Construction

Two contracts relating to twin 812mm dia. gas lines from Frigg Field.  Survey and preparation of pipeline route, 2km shore approach and pull ashore from laybarge and subsequent trenching of inshore section to give 2m of cover, using the TM IV. trenching machine.

  

Location:    Cruden Bay, Aberdeenshire, Scotland

Client:        BP Petroleum Development Ltd

Engineering, Landfall and Trenching

Pull ashore of 1km length x 812 mm dia.  Forties Field oil pipeline from laybarge and the burial of the pipe into the seabed using the TM IV trenching machine.  This was Britain’s first oil line to be landed.